Projects undertaken by ATG

 


Watermain Connection Project
Moose Factory, Ontario


New Post First Nation Terms of Reference
for a Health Centre

New Post, Ontario


Missinabie Cree First Nation Trailer Park Planning and Design
Missinabie, Ontario

Attawapiskat First Nation Aggregate Report
Attawapiskat, Ontario


Moose Cree First Nation 21 Lot Subdivision Project
Moose Factory, Ontario


Moose Cree First Nation Mapping Project
Moose Factory, Ontario

 

 

 


Watermain Connection Project
Location: Moose Factory, Ont.
Capital Cost: $121,000
Project No.: A97003

Client: Weeneebayko General Hospital
Box 664
Moose Factory, Ontario
P0L 1W0

Contact: Mr. Dave Gunner, Facilities Manager

ATG was contracted by the Weeneebayko General Hospital to design a watermain connection to the existing water distribution system. Low pressures and fire flows were creating problems and hindering development on some parts of the Island. Reviewing information from a hydraulic analysis completed by RAL Engineering/Verners Technical Services in 1995, ATG designed 500m of 250mm dia. watermain to correct these problems. Subsequent testing showed that upon completion of this project, fire flows and water pressure met acceptable standards.

 

Key Participants:

Jamie Hawken, P.Eng. Project Engineer,
Mike Faries, C.E.T. Project Manager,
Connie Gordon CAD Technician,
Jeremy Landry Survey


Attawapiskat First Nation Aggregate Report
Location: Attawapiskat, Ontario
Capital Cost: $21,000
Implementation: 1998
Project No.: A98002

Client: Attawapiskat First Nation, Tech. Services
P.O. Box 248
Attawapiskat, Ontario
P0L 1A0

Contact: Mike Gull, C.E.T.

In January 1998, ATG was contracted by the Attawapiskat First Nation (AFN) to undertake a aggregate site investigation and report. This project consisted of reviewing background information, on site topographic surveys and sampling, lab analysis, and a report. This report was required to assist the AFN in submitting an application to OMNR to extract gravel for their infrastructure requirements.

 

Key Participants:
Mike Faries, C.E.T. Project Manager,
Don Pederson, P. Eng. Project Engineer,
Bill Praskey Field Technologist


New Post First Nation Terms of Reference for a Health Centre
Location: New Post First Nation
Capital Cost: $400,000
Implementation: 1998
Project No.: A98002

Client: New Post First Nation
RR #2, Box 3310
New Post, Ontario
P0L 1C0

Contact: Nina Archibald, Housing Department

In January 1998, ATG was contracted by the New Post First Nation (NPFN) to develop a terms of reference for a Health Centre. This document will be used to assist in the NPFN tendering out a Request for Proposals for Architectural Services. Once this project is complete, the health facility will provide basic on-reserve medical services thereby eliminating the need to travel 20 km into the nearest town.

 

Key Participants:
Mike Faries, C.E.T. Consultant,
Roger Fennell Fennell Architect


Moose Cree First Nation 21 Lot Subdivision Project
Location: Moose Factory, Ont.
Capital Cost: $400,000
Project No.: A98003

Client: Moose Cree First Nation
Box 190
Moose Factory, Ontario
P0L 1W0

Contact: Mr. Les Jolly, Director of Public Works, Moose Cree First Nation

ATG was contracted by the Moose Cree First Nation (MCFN) to carry out the design of a 21 lot subdivision. This project involved a site survey using a total station and design was done with Softdesk Civil/Survey Software (CAD). Extension of roads, gravity sewers, and watermains are a part of this project. The contractor for this work is the Moose Band Development Corporation. This project will allow the MCFN to have 21 fully serviced lots by the fall, and enable them to construct houses for band members.

 

Key Participants:
Mike Faries, C.E.T. Project Manager,
Connie Gordon CAD Technician


Missinabie Cree First Nation Trailer Park Planning and Design
Location: Missinabie Cree Reserve
Capital Cost: $410,000
Project No.: A98004

Client: Missinabie Cree First Nation
RR #4, Hwy. 17E, Bell’s Point
Garden River, Ontario
P6A 5K9

Contact: Mr. Norm Hardisty, Mushkegowuk Tribal Council

Mushkegowuk Tribal Council contracted ATG to submit a preliminary design and cost estimate for this trailer park project. The drawings and estimates were used by the Missinabie Cree First Nation to assist in their land lease application with the province of Ontario.

 

Key Participants:
Mike Faries, C.E.T. Project Manager,
Jamie Hawken, P.Eng. Project Engineer


Moose Cree First Nation Mapping Project
Location: Moose Factory, Ont.
Capital Cost: $30,000
Project No.: A98005

Client: Moose Cree First Nation
Box 190
Moose Factory, Ontario
P0L 1W0

Contact: Mr. Dave Fletcher, Project Coordinator, Moose Cree First Nation

ATG was contracted by the Moose Cree First Nation (MCFN), to update its maps from a mapping project that was completed in 1993. This project encompasses the Moose Cree Traditional Territory and includes information on harvesting areas as well as historical data. This mapping will eventually be used in a GIS system that will be implemented by the MCFN.

AutoCAD Mapping

Key Participants:
Mike Faries, C.E.T. Project Manager,
Connie Gordon CAD Technician


 

BACK TO INDEX! ELDER STORY BY GILBERT G. FARIES! OUR MISSION! LET US TELL YOU ABOUT OUR SERVICES!

 

HOME ELDER STORIES MISSION PROJECTS SERVICES


 

Copyright © Aski Technology Group Ltd. 1998
Designed and maintained by InerWeb Design