After our Groundbreaking on Sunday March 18th, 2001 our new building is now under construction and will include a new worship auditorium on the upper level and classrooms on the bottom level.
As often as possible we will add some new pictures to this site to keep you up to date with the new building progress. Right now the project is scheduled to be completed in February 2002. Pictures
and Information about the construction
11/14/01 - Painting downstairs and exterior pictuuress 10/25/01 - Parking Lot and exterior shell lookingg goood 9/27/01
- Exterior shell going up/font>
9/11/01
- Bridges and Stairs poured>
7/27/01
- The Steele framing going up<
6/21/01
- Lower level walls almost done
5/31/01
- Foundation and Walls starting too goo up
4/18/01
- Digging for the foundation/font>
4/16/01
- Starting to Dig
4/9/01
- Parking lot prep
4/6/01
- Rerouting the Sewer line>
3/28/01
- First day
Architect:
Shane Brewer