Work Experience


October 1998 - Date

Working as Sub Divisional Officer S.D.O in WAPDA. Posted at the construction of Wapda House Building, Islamabad. Duties involve supervision of all construction activities including material testing, executing work as per specifications, checking of contractors bills, variation orders, time extension cases, claims etc. Project costs Rs. 100 Million.

May 1994 - October 1998

Worked as Sub Divisional Officer S.D.O in WAPDA at Ghazi Barotha Hydropower Project. Duties involved estimation of residential colony and road. Pre-construction survey / investigations of road and buildings.

Successfully completed the construction of 8 Km Dual Carriage Road (including two culverts and two bridges) in Barotha costing to Rs.40 Million. Construction activities involved survey work (joint X-sections etc.), material testing at laboratory and field, compaction tests (base, sub base, sub grade), bitumen extraction tests, checking of bills, estimates, variation orders etc.

Prepared Tender Documents for Sewerage Treatment Plant at Hattian and successfully completed the construction of the said work independently. Construction activities involved execution of work as per drawing and specifications, material testing, form work checking, steel checking etc., checking of bills, estimates, variation orders etc. Project costs Rs.15 Million.

March 1993 - April 1994

Worked as Sub Divisional Officer S.D.O in WAPDA at Pakistan Snow and Ice Hydrology project at Lahore. Involved in the construction of high altitude weather stations in the Northern Areas of Pakistan in collaboration with the Canadian consultants.

March 1992 - March 1993

Worked as Junior Engineer in WAPDA at SCARP monitoring organization at Lahore and involved in the data analysis of the SCARP tube wells and reports writing.

May 1992 - March 1992

Remained under pre-posting training at WAPDA Engineering Academy Faisalabad and WAPDA Academy Tarbela.

January 1991 - May 1991

Worked as Teacher's Assistant at the University of Houston, Texas, U.S.A and involved in the development of Structural Engineering software using Object Oriented Programming and C language.

September 1990 - December 1990

Worked as Junior Engineer (Design) at The Pakistan Engineering Associates and involved in structural designing using computer packages.

August 1989 - August 1990

Worked as Field Engineer with Nayyar Ali Dada and Associated at the construction of twenty-storied building project (Saudi Pak Tower) for SAPICO head office at Blue Area, Islamabad.